Preliminary Design
· Placement of jersey barriers for safety/traffic control
· Construction of curbing to prevent further damage
· Site meetings to develop strategy
Pre-Design
· Exploratory drilling for geotechnical information
· Analysis of test borings
· Preparation of geotechnical report
· Survey of site to obtain topographic information
· Drawing preparation of topography
Permitting
· Prepare and submit DEP permit for
stream encroachment
· PNDI Search Form
· Cultural Resource Notice
· Act 14 Notification
Design
· Design computation
· Design drawing preparation
· E & S drawings and County approval
· Specification package preparation
Preconstruction
· Advertise for bids
· Evaluate and tabulate bids
· Contract administration
Construction
· Site prep prior to construction
· Temporary paving/traffic control
· Drilling of holes into bedrock
· Placing of soldier beams into drilled holes
· Grouting of beams in rock
· Placing lagging between beams
· Backfill and compaction of suitable material
· Placement of drainage pipes during backfill
· Reconstruction of roadway to Township standard
· Replacement of guard rail
· Inspection during construction
· Preparation of as-built drawings
Restoration
·Remove temporary road
·Remove jersey barriers
·Landscaping and revegetation
The total cost of the project was $355,000.00
|